Home
 Firm
 Contact Us
 Memberships
 Affiliated Offices
 Legal System in Kuwait
 Doing Business in Kuwait
 The New Laws Proposed by the Government & Recent Developments
 Intellectual Property
 The Oil Sector
 The Law of Commissions
 The Offset Program
 Introduction
 Offset Program Objectives
 Counter-Trade Offset Program Organization
 Foreign Contractor and Offset Obligation
 Overview of the Offset Program Process
 The Offset Business Venture
 Fulfillment of the Offset Obligation
 Offset Milestone Schedule
 Penalties
 Islamic Laws, Fianance and Banking
 Iraq Reconstruction Projects
 Picture Gallery
 Recent Awards
 Clients


 

 

Offset Milestone Schedule

The effective date of commencement of the offset obligation is the date of signing the supply contract. This date is called the Offset Start Date (OSD). In certain circumstances where the date of signing and the effective date of commencement of the supply contract is different such that the difference between the two dates exceeds 90 days and such difference is material, or due to any material changes to the supply contract schedule not attributable to the foreign contractor's performance, then the foreign contractor may petition the PEO to adjust his OSD appropriately.

An offset milestone schedule lays down the time limits within which the offset obligation is to be performed.

Penalties

The imposition and enforcement of penalties is left to the discretion of the government of the State of Kuwait. Provisions are made for imposition of non-participation penalty and partial fulfillment penalty.